Power Generation2024 · Case Study

Hospital campus standby generation plant

Los Angeles, CA · 2 MW diesel + paralleling

A Level 1 standby plant for a regional hospital: two paralleled 1 MW gensets, closed-transition transfer and life-safety branch distribution to OR, ICU and imaging — certified to NFPA 110.

Generators
2 × 1 MW
Voltage
480V / 3Ø
Transfer
Closed-transition ATS
Code
NFPA 110 / CEC 700
Hospital campus standby generation plant
01Scope of Work

What we were engaged to build.

Two 1 MW standby gensets with synchronizing switchgear and automatic load-step sequencing.
Closed-transition transfer with soft-load controls for no-break switchover to utility.
Black-start capability and monthly load-bank testing for NFPA 110 Level 1 compliance.
Utility interlock and protective relaying (27/59/81/32/46) coordinated with the serving utility.
Dual-wall sub-base fuel tanks sized for 96 hours of rated standby operation.
Life-safety and critical branch distribution to OR, ICU and imaging suites per CEC Article 517.
02Technical Specifications

Actual ratings, devices and standards.

The service voltages, equipment ratings, protective functions and codes this project was built and tested against.

Gensets
2× 1,000 kW, 1,250 kVA, 480V @ 0.8 PF
Paralleling
Synchronizing switchgear, load-demand
ATS
4,000A closed-transition, soft-load (no-break)
Fuel
Dual-wall 8,000 gal sub-base, 96-hr run
Black start
Battery + charger, 10-sec start
Relaying
27/59/81/32/46, IEEE 1547 interlock
Life-safety
CEC 700, 701, 517 branches
Testing
Monthly load-bank, annual full-load
03Solutions Deployed

The specific electrical solutions we used.

How each design decision solved a real constraint on this project — from redundancy and coordination to protection and commissioning.

01

Paralleled 1 MW gensets with load-demand

The paralleling gear runs one genset at light load and starts the second only when demand rises, so the plant avoids wet-stacking and the hospital never runs a 2 MW plant at 20% load.

02

Closed-transition, no-break transfer

The ATS synchronizes to utility before transferring back, so the switch is a no-break event — critical for imaging and anesthesia equipment that can’t ride a 10-second outage.

03

NFPA 110 Level 1 compliance program

Weekly inspections, monthly load-bank runs and annual full-load tests are documented to the NFPA 110 record, keeping the Level 1 classification that accreditors audit.

04

CEC 517 critical branch segregation

The critical and life-safety branches are on their own transfer switches and panels, so a fault on a non-essential branch can never take down the OR or ICU.

04On Site

From the build.

Hospital campus standby generation plant — view 1
Hospital campus standby generation plant — view 2
Hospital campus standby generation plant — view 3